Home > Practice > Arithmetic Aptitude > Chain Rule > Miscellaneous
1. 3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?
More pumps, Less working hours per day (Indirect Proportion)
Less days, More working hours per day (Indirect Proportion)
Solution:
Let the required number of working hours per day be x.More pumps, Less working hours per day (Indirect Proportion)
Less days, More working hours per day (Indirect Proportion)