1. 30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers to finish the same piece of work in 30 days, will be ?

Solution:
Let the required number of labourers be x
Less working hour/day, More labours (Indirect proportion)
More days, Less labourers (Indirect proportion)
Working hours/day 6:7Days 30:18}::30:x
6×30×x=7×18×306x=126x=21