1. A can finish a piece of work in 18 days and B can do the same work in half of the time taken by A. Then working together what part of the same work they can finish in a day ?

Solution:
So let's solve now,
A's 1 day work = 118
B's 1 day work = 19 [because B take half time than A]
(A + B)'s one day work
=118+19=1+218=16