Home > Practice > Arithmetic Aptitude > Time and Work > Miscellaneous
1. A complete 710 of a work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many day A and B can complete entire work together?

Solution:
710 part of work has been completed by A in 15 days. Then,
Rest work = 1 - 710 = 310 part
Given, That 310 part of the work is completed by A and B together in 4 days. Means,
(A + B) completed the 310 of work in 4 days
So, (A + B)'s 1 day's work = 310×4  = 340
Hence,
(A + B) can complete the work in 403 = 1313 days