Home > Practice > Arithmetic Aptitude > Chain Rule > Miscellaneous
1. A contract is to be complete in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47  of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

Solution:
Remaining work
= (147) = 37
Remaining period = (46 - 33) = 13 days
Let the total men working at it be x
Less work, Less men (Direct proportion)
Less days, More men (Indirect proportion)
More hour/day, Less men (Indirect proportion)
Work 47:37Men 13:33Hour/day 9:8}::117:x
 47×13×9×x=37×33×8×117x=(3×33×8×117)(4×13×9)x=198
∴ Addition men to be employed = (198 - 117) = 81

You must login to add comments. Login now.