Home > Practice > Arithmetic Aptitude > Time and Work > Miscellaneous
1. A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?

Solution:
Given,
A is 60% more efficient of B Means,
A=B+60%of BA=B+60B100A=100B+60B100A=160B100A=8B5
A can complete whole work in 15 days. So,
One day work of A = 115
One day work of A = 8B5 = 115
One day work of B = 5120 = 124
One day work, (A + B) = 115+124
One day work, (A + B) = 24+15360   = 39360
So, Time taken to finish the work by A and B together = 36039 = 12013 days

Alternatively
We can solve it through percentage method
Given,
A = 8B5
A can complete whole work in 15 days
Work rate of A = 10015 = 6.66% per day
Work rate of 8B5 = 6.66%
Work rate of B = 4.16% per day
Work rate of (A + B) = 6.66 + 4.16 = 10.82% per day
So, A and B can complete 100% work in 12013 days