1. If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:

Solution:
Here, we use work equivalence method;
10 × 12 = 12 × x
Or, x = 10 days

To understand the work equivalence method, we use a graphic as follows:

Men   Days
10 ↓    12
12     ↑ x (let)
Here, the two arrows, downward (↓) and upward (↑) show variation between men and days.
[If downward arrows show decrements then upward arrows show increments and vice-verse.]
Thus,
1012=x12or, x=10×1212=10days