1. If 17 labourers can dig a ditch 26 m long in 18 days, working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day ?

Solution:
Let the total number of men to be engaged be x
More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
Lentgh 26:39Days 6:18Hours per day 9:8}::17:x
 26×6×9×x=39×18×8×17x=(39×18×8×17)(26×6×9)x=68
∴ Number of more labourers = (68 -17) = 51