1. If 17 labourers can dig a ditch 26 m long in 18 days, working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day ?
More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
∴ Number of more labourers = (68 -17) = 51
Solution:
Let the total number of men to be engaged be More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
∴ Number of more labourers = (68 -17) = 51