1. If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

Solution:
1st method:
A and B complete a work in = 15 days
One day's work of (A + B) = 115
B complete the work in = 20 days;
One day's work of B = 120
Then, A's one day's work
=115120=436=160
Thus, A can complete the work in = 60 days.

2nd method:
(A + B)'s one day's % work = 10015 = 6.66%
B's one day's % work = 10020 = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = 1001.66 = 60 days to complete the work.