Home > Practice > Arithmetic Aptitude > Time and Work > Miscellaneous
1. If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?
A and B complete a work in = 15 days
One day's work of (A + B) =
B complete the work in = 20 days;
One day's work of B =
Then, A's one day's work
Thus, A can complete the work in = 60 days.
2nd method:
(A + B)'s one day's % work = = 6.66%
B's one day's % work = = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = = 60 days to complete the work.
Solution:
1st method:A and B complete a work in = 15 days
One day's work of (A + B) =
B complete the work in = 20 days;
One day's work of B =
Then, A's one day's work
Thus, A can complete the work in = 60 days.
2nd method:
(A + B)'s one day's % work = = 6.66%
B's one day's % work = = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = = 60 days to complete the work.