1. While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?
1 hour's work of A =
B can complete the work in 7 × 8 = 56 hours
1 hour's work of B =
(A + B)'s 1 hour's work
∴ Time taken by (A + B) working 8 hours daily
Solution:
A can complete the work in 7 × 6 = 42 hours1 hour's work of A =
B can complete the work in 7 × 8 = 56 hours
1 hour's work of B =
(A + B)'s 1 hour's work
∴ Time taken by (A + B) working 8 hours daily