41. If 12 carpenters, working 6 hours a day, can make 460 chairs in 24 days, how many chairs will 18 carpenters make in 36 days, each working 8 hours a day ?

Discuss
Solution:
Let the required number of chairs be x
Then, More carpenters, More chairs (Direct proportion)
More hours per day, More chairs (Direct proportion)
More days, More chairs (Direct proportion)
Carpenters 12:18Hours per day 6:8Days 24:36}::460:x
 12×6×24×x=18×8×36×460x=(18×8×36×460)(12×6×24)x=1380
∴ Required number of chairs = 1380
42. If 5 spiders can catch five files in five minutes, how many files can hundred spiders catch in 100 minutes ?

Discuss
Solution:
Let the required number of chairs be x.
Then, More spiders, More flies (Direct proportion)
More time, More flies (Direct proportion)
Spiders 5:100Minutes 5:100}::5:x
 5×5×x=100×100×5x=(100×100×5)(5×5)x=2000
43. 2 persons working 2 hours a day assemble 2 machine in 2 days. The number of machines assemble by 6 persons working 6 hours a day in 6 day is ?

Discuss
Solution:
Let the required number of machine be x
More persons, More machines (Direct proportion)
More working working hours, More machines (Direct proportion)
More days, More machines (Direct proportion)
Persons 2:6Working hours 2:6Days 2:6}::2:x
 2×2×2×x=6×6×6×2x=(6×6×6×2)(2×2×2)x=54
44. A wall of 100 meters can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres ?

Discuss
Solution:
Let the required number of days be x
7 men = 10 women
(14 men and 20 women) = (20 + 20) women = 40 women
More length, More days (Direct proportion)
More women, Less days (Indirect proportion)
Length 100:600Women 40:10}::10:x
 100×40×x=600×10×10x=(600×10×10)(100×40)x=15
45. 21 binders can bind 1400 books in 15 days. How many binders will required to bind 800 books in 20 days ?

Discuss
Solution:
Let the required number of binders be x
Less books, Less binders (Direct proportion)
More days, Less binders (Indirect proportion)
Books 1400:800Days 20:15}::21:x
 1400×20×x=800×15×21x=(800×15×21)(1400×20)x=9
46. If 17 labourers can dig a ditch 26 m long in 18 days, working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day ?

Discuss
Solution:
Let the total number of men to be engaged be x
More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
Lentgh 26:39Days 6:18Hours per day 9:8}::17:x
 26×6×9×x=39×18×8×17x=(39×18×8×17)(26×6×9)x=68
∴ Number of more labourers = (68 -17) = 51
47. 20 men complete one-third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days ?

Discuss
Solution:
Let the total number of men be x
Work done = 13
Remaining work
= (113)=23
More work, More men (Direct proportion)
More days, Less men (Indirect proportion)
Work 13:23Days 25:20}::20:x
 (13×25×x)=(23×20×20)x=80025x=32
∴ More men to be employed = (32 - 20) = 12
48. A rope makes 70 rounds of the circumference of a cylinder whose radius of the base is 14 cm. How many times can it go round a cylinder with radius 20 cm ?

Discuss
Solution:
Let the required number of rounds be x
More radius, Less rounds (Indirect proportion)
 20:14::70:x(20×x)=(14×70)x=(14×70)20x=49
49. A contract is to be complete in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47  of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

Discuss
Solution:
Remaining work
= (147) = 37
Remaining period = (46 - 33) = 13 days
Let the total men working at it be x
Less work, Less men (Direct proportion)
Less days, More men (Indirect proportion)
More hour/day, Less men (Indirect proportion)
Work 47:37Men 13:33Hour/day 9:8}::117:x
 47×13×9×x=37×33×8×117x=(3×33×8×117)(4×13×9)x=198
∴ Addition men to be employed = (198 - 117) = 81
50. 12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time ?

Discuss
Solution:
Let the required number of persons be x
Less days , More persons (Indirect proportion)
More work , More persons (Direct proportion)
Days 2:4Work 1:8}::12:x
2×1×x=4×8×12x=(4×8×12)(2)x=192