Home > Practice > Arithmetic Aptitude > Chain Rule > Miscellaneous
41. If 12 carpenters, working 6 hours a day, can make 460 chairs in 24 days, how many chairs will 18 carpenters make in 36 days, each working 8 hours a day ?
Then, More carpenters, More chairs (Direct proportion)
More hours per day, More chairs (Direct proportion)
More days, More chairs (Direct proportion)
∴ Required number of chairs = 1380
Solution:
Let the required number of chairs be xThen, More carpenters, More chairs (Direct proportion)
More hours per day, More chairs (Direct proportion)
More days, More chairs (Direct proportion)
∴ Required number of chairs = 1380
42. If 5 spiders can catch five files in five minutes, how many files can hundred spiders catch in 100 minutes ?
Then, More spiders, More flies (Direct proportion)
More time, More flies (Direct proportion)
Solution:
Let the required number of chairs be x.Then, More spiders, More flies (Direct proportion)
More time, More flies (Direct proportion)
43. 2 persons working 2 hours a day assemble 2 machine in 2 days. The number of machines assemble by 6 persons working 6 hours a day in 6 day is ?
More persons, More machines (Direct proportion)
More working working hours, More machines (Direct proportion)
More days, More machines (Direct proportion)
Solution:
Let the required number of machine be xMore persons, More machines (Direct proportion)
More working working hours, More machines (Direct proportion)
More days, More machines (Direct proportion)
44. A wall of 100 meters can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres ?
7 men = 10 women
(14 men and 20 women) = (20 + 20) women = 40 women
More length, More days (Direct proportion)
More women, Less days (Indirect proportion)
Solution:
Let the required number of days be x7 men = 10 women
(14 men and 20 women) = (20 + 20) women = 40 women
More length, More days (Direct proportion)
More women, Less days (Indirect proportion)
45. 21 binders can bind 1400 books in 15 days. How many binders will required to bind 800 books in 20 days ?
Less books, Less binders (Direct proportion)
More days, Less binders (Indirect proportion)
Solution:
Let the required number of binders be xLess books, Less binders (Direct proportion)
More days, Less binders (Indirect proportion)
46. If 17 labourers can dig a ditch 26 m long in 18 days, working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day ?
More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
∴ Number of more labourers = (68 -17) = 51
Solution:
Let the total number of men to be engaged be More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
∴ Number of more labourers = (68 -17) = 51
47. 20 men complete one-third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days ?
Work done =
Remaining work
=
More work, More men (Direct proportion)
More days, Less men (Indirect proportion)
∴ More men to be employed = (32 - 20) = 12
Solution:
Let the total number of men be xWork done =
Remaining work
=
More work, More men (Direct proportion)
More days, Less men (Indirect proportion)
∴ More men to be employed = (32 - 20) = 12
48. A rope makes 70 rounds of the circumference of a cylinder whose radius of the base is 14 cm. How many times can it go round a cylinder with radius 20 cm ?
More radius, Less rounds (Indirect proportion)
Solution:
Let the required number of rounds be xMore radius, Less rounds (Indirect proportion)
49. A contract is to be complete in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
=
Remaining period = (46 - 33) = 13 days
Let the total men working at it be x
Less work, Less men (Direct proportion)
Less days, More men (Indirect proportion)
More hour/day, Less men (Indirect proportion)
∴ Addition men to be employed = (198 - 117) = 81
Solution:
Remaining work=
Remaining period = (46 - 33) = 13 days
Let the total men working at it be x
Less work, Less men (Direct proportion)
Less days, More men (Indirect proportion)
More hour/day, Less men (Indirect proportion)
∴ Addition men to be employed = (198 - 117) = 81
50. 12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time ?
Less days , More persons (Indirect proportion)
More work , More persons (Direct proportion)
Solution:
Let the required number of persons be xLess days , More persons (Indirect proportion)
More work , More persons (Direct proportion)