Home > Practice > Arithmetic Aptitude > Time and Work > Miscellaneous
1. If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?
A and B complete a work in = 15 days
One day's work of (A + B) =
B complete the work in = 20 days;
One day's work of B =
Then, A's one day's work
Thus, A can complete the work in = 60 days.
2nd method:
(A + B)'s one day's % work = = 6.66%
B's one day's % work = = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = = 60 days to complete the work.
Solution:
1st method:A and B complete a work in = 15 days
One day's work of (A + B) =
B complete the work in = 20 days;
One day's work of B =
Then, A's one day's work
Thus, A can complete the work in = 60 days.
2nd method:
(A + B)'s one day's % work = = 6.66%
B's one day's % work = = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = = 60 days to complete the work.
2. If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:
Solution:
3. A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
(A+B)'s one day's work = part
(A+B) works 2 days together = part
Remaining work = = part
part of work is completed by A in two days
Hence, one day's work of A =
Then, one day's work of B = =
So, B alone can complete the whole work in 6 days.
2nd Method:
(A+B)'s one day's % work = = 33.3%
Work completed in 2 days = 66.6%
Remaining work = 33.4%
One day's % work of A = = 16.7%
One day's work of B = 33.4 - 16.7 = 16.7%
B alone can complete the work in,
=
= 5.98 days
≈ 6 days.
Solution:
1st Method:(A+B)'s one day's work = part
(A+B) works 2 days together = part
Remaining work = = part
part of work is completed by A in two days
Hence, one day's work of A =
Then, one day's work of B = =
So, B alone can complete the whole work in 6 days.
2nd Method:
(A+B)'s one day's % work = = 33.3%
Work completed in 2 days = 66.6%
Remaining work = 33.4%
One day's % work of A = = 16.7%
One day's work of B = 33.4 - 16.7 = 16.7%
B alone can complete the work in,
=
= 5.98 days
≈ 6 days.
4. A can complete a piece of work in 18 days, B in 20 days and C in 30 days, B and C together start the work and forced to leave after 2 days. The time taken by A alone to complete the remaining work is:
2nd Method:
% of work B completes in one day = = 5%;
% of work C completes in one day = = 3.33%;
% of work (A + B) completes together in one day = 5 + 3.33 = 8.33%;
% work (A + B) completes together in 2 days = 8.66 × 2 = 16.66%;
Remaining work = 100 - 16.66 = 83.34%;
% of work A completes in 1 day = = 5.55%
Time taken to complete the remaining work by A
=
= 15 days
Solution:
1st Method:2nd Method:
% of work B completes in one day = = 5%;
% of work C completes in one day = = 3.33%;
% of work (A + B) completes together in one day = 5 + 3.33 = 8.33%;
% work (A + B) completes together in 2 days = 8.66 × 2 = 16.66%;
Remaining work = 100 - 16.66 = 83.34%;
% of work A completes in 1 day = = 5.55%
Time taken to complete the remaining work by A
=
= 15 days
5. Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:
Working 5 hours a day, A can complete the work in 8 days i.e.
= 5 × 8 = 40 hours
Working 6 hours a day, B can complete the work in 10 days i.e.
= 6 × 10 = 60 hours
(A + B)'s 1 hour's work,
Hence, A and B can complete the work in 24 hours i.e. they require 3 days to complete the work.
2nd Method:
% 1 hour's work of A = = 2.5%
% 1 hour's work of B = = 1.66%
(A + B) one hour's % work,
= (2.5 + 1.66) = 4.16%
Time to complete the work,
= = 24 hours
Then, = 3 days
They need 3 days, working 8 hours a day to complete the work.
Solution:
1st Method:Working 5 hours a day, A can complete the work in 8 days i.e.
= 5 × 8 = 40 hours
Working 6 hours a day, B can complete the work in 10 days i.e.
= 6 × 10 = 60 hours
(A + B)'s 1 hour's work,
Hence, A and B can complete the work in 24 hours i.e. they require 3 days to complete the work.
2nd Method:
% 1 hour's work of A = = 2.5%
% 1 hour's work of B = = 1.66%
(A + B) one hour's % work,
= (2.5 + 1.66) = 4.16%
Time to complete the work,
= = 24 hours
Then, = 3 days
They need 3 days, working 8 hours a day to complete the work.
6. Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?

According to question,
Ganga begins at 9 am and she does 3 units/hours
Saraswati begins at 10 am and she does 2 units/hours
So by 11 am they complete 5 units
Time
(4 cycle of 2 hrs each + 4 units left)
And now ganga will complete 3 unit out of 4 units in 1 hr
Now, rest 1 unit work done by = hr
Total time = 8 + 1 + = 9 hr
Hence,Work finished at
= 9 am + 9 hr
= 6:30 PM
Alternate Solution:
Work done by Ganga in 1 hour =
Work done by Saraswati in 1 hour =
They are working alternatively with Ganga beginning the job.
Work done in every two hours = + =
Work done in 4 × 2 = 8 hours = =
Remaining work = 1 - =
In 9th hour, Ganga starts the work and does of the work
Work remaining = - =
In 10th hour, Saraswati starts the work
Time needed to finish the remaining work
0.5 hours
30 minutes
i.e., work will be completed in 9 hour 30 minutes, after 9 AM
i.e., at 6:30 PM
Solution:

According to question,
Ganga begins at 9 am and she does 3 units/hours
Saraswati begins at 10 am and she does 2 units/hours
So by 11 am they complete 5 units
Time
(4 cycle of 2 hrs each + 4 units left)
And now ganga will complete 3 unit out of 4 units in 1 hr
Now, rest 1 unit work done by = hr
Total time = 8 + 1 + = 9 hr
Hence,Work finished at
= 9 am + 9 hr
= 6:30 PM
Alternate Solution:
Work done by Ganga in 1 hour =
Work done by Saraswati in 1 hour =
They are working alternatively with Ganga beginning the job.
Work done in every two hours = + =
Work done in 4 × 2 = 8 hours = =
Remaining work = 1 - =
In 9th hour, Ganga starts the work and does of the work
Work remaining = - =
In 10th hour, Saraswati starts the work
Time needed to finish the remaining work
0.5 hours
30 minutes
i.e., work will be completed in 9 hour 30 minutes, after 9 AM
i.e., at 6:30 PM
7. If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:
10 × 12 = 12 × x
Or, x = 10 days
To understand the work equivalence method, we use a graphic as follows:
Men Days
10 ↓ 12
12 ↑ x (let)
Here, the two arrows, downward (↓) and upward (↑) show variation between men and days.
[If downward arrows show decrements then upward arrows show increments and vice-verse.]
Thus,
Solution:
Here, we use work equivalence method;10 × 12 = 12 × x
Or, x = 10 days
To understand the work equivalence method, we use a graphic as follows:
Men Days
10 ↓ 12
12 ↑ x (let)
Here, the two arrows, downward (↓) and upward (↑) show variation between men and days.
[If downward arrows show decrements then upward arrows show increments and vice-verse.]
Thus,
8. To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
B alone can complete the work in
Solution:
B alone can complete the work in
9. If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?
→1 men = 2 boys
8 men = 2 × 8 boys = 16 boys
Then,
(16 boys + 4 boys) = 20 boys can make 260 mats in 20 days
Now,
It can be calculated by work equivalence method:
20 × 260 × 20 = x × 20 × 20
x = 260 mats
Solution:
10 men = 20 boys→1 men = 2 boys
8 men = 2 × 8 boys = 16 boys
Then,
(16 boys + 4 boys) = 20 boys can make 260 mats in 20 days
Now,
It can be calculated by work equivalence method:
20 × 260 × 20 = x × 20 × 20
x = 260 mats
10. A complete of a work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many day A and B can complete entire work together?
Rest work = 1 - = part
Given, That part of the work is completed by A and B together in 4 days. Means,
(A + B) completed the of work in 4 days
So, (A + B)'s 1 day's work = =
Hence,
(A + B) can complete the work in = days
Solution:
part of work has been completed by A in 15 days. Then,Rest work = 1 - = part
Given, That part of the work is completed by A and B together in 4 days. Means,
(A + B) completed the of work in 4 days
So, (A + B)'s 1 day's work = =
Hence,
(A + B) can complete the work in = days
Previous