Home > Practice > Arithmetic Aptitude > Time and Work > Miscellaneous
1. If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

Discuss
Solution:
1st method:
A and B complete a work in = 15 days
One day's work of (A + B) = 115
B complete the work in = 20 days;
One day's work of B = 120
Then, A's one day's work
=115120=436=160
Thus, A can complete the work in = 60 days.

2nd method:
(A + B)'s one day's % work = 10015 = 6.66%
B's one day's % work = 10020 = 5%
A's one day's % work = 6.66 - 5 = 1.66%
Thus, A need = 1001.66 = 60 days to complete the work.
2. If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:

Discuss
Solution:
Oneday'sworkof(A+B)=118.......(1)Oneday'sworkof(A+C)=112.......(2)Oneday'sworkof(B+C)=19.......(3)Adding(1),(2)and(3)2×(A+B+C)=118+112+192(A+B+C)=14One day's work ofA+B+C=18B=18(A+C)B=18112One day's work ofB=3224=124Bneed24days
3. A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

Discuss
Solution:
1st Method:
(A+B)'s one day's work = 13 part
(A+B) works 2 days together = 23 part
Remaining work = 123  = 13 part
13 part of work is completed by A in two days
Hence, one day's work of A = 16
Then, one day's work of B = 1316  = 16
So, B alone can complete the whole work in 6 days.

2nd Method:
(A+B)'s one day's % work = 1003 = 33.3%
Work completed in 2 days = 66.6%
Remaining work = 33.4%
One day's % work of A = 33.42 = 16.7%
One day's work of B = 33.4 - 16.7 = 16.7%
B alone can complete the work in,
= 10016.7
= 5.98 days
≈ 6 days.
4. A can complete a piece of work in 18 days, B in 20 days and C in 30 days, B and C together start the work and forced to leave after 2 days. The time taken by A alone to complete the remaining work is:

Discuss
Solution:
1st Method:
(B+C)2dayswork=2×(120+130)=2×3+260=16partRemainingwork=116=56partA'soneday'swork=118partTime taken to complete the work=56118daysHence,Time taken to complete the work=56×18=15days

2nd Method:
% of work B completes in one day = 10020 = 5%;
% of work C completes in one day = 10030 = 3.33%;
% of work (A + B) completes together in one day = 5 + 3.33 = 8.33%;
% work (A + B) completes together in 2 days = 8.66 × 2 = 16.66%;
Remaining work = 100 - 16.66 = 83.34%;
% of work A completes in 1 day = 10018 = 5.55%
Time taken to complete the remaining work by A
= 83.345.55
= 15 days
5. Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:

Discuss
Solution:
1st Method:
Working 5 hours a day, A can complete the work in 8 days i.e.
= 5 × 8 = 40 hours
Working 6 hours a day, B can complete the work in 10 days i.e.
= 6 × 10 = 60 hours
(A + B)'s 1 hour's work,
=140+160=3+2120=5120=124
Hence, A and B can complete the work in 24 hours i.e. they require 3 days to complete the work.

2nd Method:
% 1 hour's work of A = 10040 = 2.5%
% 1 hour's work of B = 10060 = 1.66%
(A + B) one hour's % work,
= (2.5 + 1.66) = 4.16%
Time to complete the work,
= 1004.16 = 24 hours
Then, 248 = 3 days
They need 3 days, working 8 hours a day to complete the work.
6. Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?

Discuss
Solution:
Time and Work mcq solution image
According to question,
Ganga begins at 9 am and she does 3 units/hours
Saraswati begins at 10 am and she does 2 units/hours
So by 11 am they complete 5 units
Time =T.W.3+2=245
(4 cycle of 2 hrs each + 4 units left)
And now ganga will complete 3 unit out of 4 units in 1 hr
Now, rest 1 unit work done by = 12 hr
Total time = 8 + 1 + 12 = 912 hr
Hence,Work finished at
= 9 am + 912 hr
= 6:30 PM
Alternate Solution:
Work done by Ganga in 1 hour = 18
Work done by Saraswati in 1 hour = 112
They are working alternatively with Ganga beginning the job.
Work done in every two hours = 18 + 112 = 524
Work done in 4 × 2 = 8 hours = 5×424 = 56
Remaining work = 1 - 56 = 16
In 9th hour, Ganga starts the work and does 18 of the work
Work remaining = 16 - 18 = 124
In 10th hour, Saraswati starts the work
Time needed to finish the remaining work
=124112=124×12
  = 0.5 hours
  = 30 minutes
i.e., work will be completed in 9 hour 30 minutes, after 9 AM
i.e., at 6:30 PM
7. If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:

Discuss
Solution:
Here, we use work equivalence method;
10 × 12 = 12 × x
Or, x = 10 days

To understand the work equivalence method, we use a graphic as follows:

Men   Days
10 ↓    12
12     ↑ x (let)
Here, the two arrows, downward (↓) and upward (↑) show variation between men and days.
[If downward arrows show decrements then upward arrows show increments and vice-verse.]
Thus,
1012=x12or, x=10×1212=10days
8. To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

Discuss
Solution:
We haveB=32×AA=23×BOne day's work,A+B=11823×B+B=11853×B=118Oneday'sworkofB=390
B alone can complete the work in
=903=30days
9. If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?

Discuss
Solution:
10 men = 20 boys
→1 men = 2 boys
8 men = 2 × 8 boys = 16 boys
Then,
(16 boys + 4 boys) = 20 boys can make 260 mats in 20 days
Now,
It can be calculated by work equivalence method:
20 × 260 × 20 = x × 20 × 20
x = 260 mats
10. A complete 710 of a work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many day A and B can complete entire work together?

Discuss
Solution:
710 part of work has been completed by A in 15 days. Then,
Rest work = 1 - 710 = 310 part
Given, That 310 part of the work is completed by A and B together in 4 days. Means,
(A + B) completed the 310 of work in 4 days
So, (A + B)'s 1 day's work = 310×4  = 340
Hence,
(A + B) can complete the work in 403 = 1313 days